Cold Warehouse Flooring

Posted on Posted in Industrial

Cold Warehouse Flooring Applied with Self Leveling Epoxy

Surface Condition

The cold warehouse flooring was perfectly prepped by our team. The concrete was old and had major cracks and dilapidated areas. There were also rubber in between construction joints which has to be removed and filled. The floor had no signs of grease and oil which is great.

Surface Preparation

The surface preparation team first needed to remove the rubber filling in between construction joints. The area was then prepared  using a Planetary Grinder with a planing attachment. All this grinding must have minimal dust so there is a vacuum attachment with all the machines used.

Primer and Repair

Epoxy Mortar was then used to fill in the deep concrete joints. It was then applied with Carmacoat Epoxy Putty to even out the areas in preparation for the Topcoat. Then Carmacoat Epoxy Primer was applied in segments as the area had other contractors with different works. Then another application of Carmacoat Epoxy Putty was applied to the entire area. The team had full communication with the main contractor in every step.


The application of Carmacoat Self-Leveling Topcoat to the warehouse flooring was applied per room. This was done to ensure a seamless finish in every room.

Coving Coating

Then we applied the final coat for their concrete coving. The concrete coving was done by the main contractor, we just needed to paint it in order for a hygenic finish.


The project took 1 month as there were ongoing works from various trades. The coordination of our team and the main contractor made this project successful. Planning and execution are the key to every project.